Islamabad, Aug 31: The Ravi Urban Development Authority (RUDA) posted on their official Facebook handle that major progress has been made in Chahar Bagh as construction continues.

Based on the specifics, the most recent infrastructure report shows significant advancements: the earthwork is almost finished at 99%, the drainage system is finished, and the sewage system is 98% complete. Overhead water tanks are 82% completed, while the boundary wall is 92% finished. Water supply installation is at 64%, while sub-base and base course works are at 69%. In total, 70.6% of the project has been completed. For more developments, stay tuned to Zameen News.